Iran Amir Kabir ( Ex. Iran Alborz
)SUBMERSIBLE DRILLING UNITPROJECT (IAKSSDU)U

|
Project
Particulars |
|
Name of Project |
: |
Iran Amir Kabir ( Ex. Iran
Alborz )SUBMERSIBLE DRILLING UNITPROJECT (IAKSSDU) |
|
Employer |
: |
NIOC – KEPCO |
|
Contractor |
: |
SADRA-GVA C
Consortium |
|
Location of
implementation |
: |
Neka – Sadra
Shipyard |
|
Delivery date |
: |
2009 |
|
Cost |
: |
302 Million USD |
Main Dimension
•
Length over
all 98.60 m
•
Breadth over all (less
bolsters) 78.80 m
•
Height, keel to upper
deck 36.50 m
•
Height, to lower
deck 29.70 m
•
Height, keel to bottom of
top box 28.50 m
Pontoons
•
Length over all
80.56 m
•
Breadth over
all 18.68 m
•
Depth
7.50
m
Columns
Circular columns 12.90
m diameter
Scope of work of APS for Supervision to EPC Contract
Supervision to Eng.
|
Supervision to
Execution
|
|
Concep. Des. |
Basic
Des. |
Detail Des.
|
M.C.
|
High Supervision
|
Site Supervision.
|
|
ü |
ü |
ü |
ü |
ü |
ü |
 |
2

Project
Particulars
|
Name of Project |
: |
Three Multi
Purpose Supply Vessels Project |
|
Employer |
: |
NIOC - KEPCO |
|
Contractor |
: |
SADRA |
|
Location of
implementation |
: |
Neka – Sadra
Shipyard |
|
Delivery date |
: |
2008 |
|
Cost |
: |
About 70
Million USD |
Principal
Particulars:
|
Length Over All |
: |
74.40m |
|
Length Betw. Perp |
: |
66.48m |
|
Breadth Mld. |
: |
16.00m |
|
Depth To 1st deck |
: |
7.60m |
|
Scantling Draught |
: |
6.84m |
|
Frame Spacing |
: |
0.60/0.72/0.60m |
|
Bollard Pull |
: |
180 tonnes |
Scope of work of APS for Supervision to EPC Contract
Supervision to Eng.
|
Supervision to
Execution
|
|
Concep. Des. |
Basic
Des. |
Detail Des.
|
M.C.
|
High Supervision
|
Site Supervision.
|
|
ü |
ü |
ü |
ü |
ü |
ü |
 |
3

|
Project
Particulars |
|
Name of Project |
: |
New Building
and Repair Yard Project |
|
Employer |
: |
Iran Ship
Building & Offshore Industries Complex (ISOICO) |
|
Contractor |
: |
Various Iranian
& INT. Companies |
|
Location of
implementation |
: |
BANDAR - ABBAS |
|
Delivery date |
: |
2010 |
|
Cost |
: |
First Phase
about 473 million USD, total about 700 million
USD (Estimated) |
Scope of work of APS for Engineering Services rendered
for the Project
Eng.
|
Supervision to
Execution
|
|
Mother consultant |
Basic
Des. |
Detail Des.
|
M.C.
|
High Supervision
|
Site Supervision..
|
|
ü |
ü |
ü |
|
ü |
ü |
top |
4
NEKA INTEGRATED HARBOR EXTENSION PROJECT
|
Project
Particulars
|
|
Name of Project |
: |
Neka Integrated
Harbor Breakwater & Dredging |
|
Employer |
: |
NIOC |
|
Contractor |
: |
To be tendered |
|
Location of
implementation |
: |
Neka |
|
Delivery date |
: |
2012 |
|
Cost |
: |
125 million USD
(Estimated) |
Scope of work of APS for Supervision
to EPC Contract
Supervision to Eng.
|
Supervision to
Execution
|
|
Concep.Des. |
Basic
Des. |
Detail Des.
|
M.C.
|
High Supervision
|
Site Supervision..
|
|
ü |
ü |
ü |
ü |
ü |
ü |
 |
5

|
Project Particulars |
|
Name of Project |
: |
Launching &
Docking Facilities at Arvandan Shipyard |
|
Employer |
: |
Arvandan Ship
Building Company |
|
Contractor |
: |
Azar-Simab |
|
Location of
implementation |
: |
Khoramshahr |
|
Delivery date |
: |
2008 |
|
Cost |
: |
10 million USD |
Principal Particulars
|
Length (Basin) |
: |
76.30m |
|
Width (Basin) |
: |
40.00m |
|
Launching Basin Dept. |
: |
3.60m |
|
Stilling Basin Dept. |
: |
6.50m |
|
Length (Design Ship) |
: |
60.00m |
|
Wight (Design Ship) |
: |
13.00m |
|
Light Weight (Design Ship) |
: |
470 ton |
Scope of work of APS for Lunching & Docking Facilities
Eng.
|
Supervision to
Execution
|
|
Concep.Des |
Basic
Des. |
Detail Des.
|
M.C.
|
High Supervision
|
Site Supervision..
|
|
ü |
ü |
ü |
|
ü |
ü |
 |
6
|
Project Particulars |
|
Name of Project |
: |
International
Marine Terminal |
|
Employer |
: |
Port and
Shipping Organization (PSO) |
|
Contractor |
: |
Toseeh Maskan
Organization |
|
Location of
implementation |
: |
Bandar Abbas |
|
Delivery date |
: |
1996 |
|
Cost |
: |
6 million USD |
Scope of work of APS for International Marin Terminal
Eng.
|
Supervision to
Execution
|
|
Concep. Des. |
Basic
Des. |
Detail Des.
|
M.C.
|
High Supervision
|
Site Supervision..
|
|
ü |
ü |
ü |
|
ü |
ü |
 |
7

|
Project Particulars |
|
Name of Project |
: |
Gama Khodro
Main Production Hall & Underneath Gear-Box
assembly Hall |
|
Employer |
: |
Pars Khodro |
|
Contractor |
: |
Alout Company |
|
Location of
implementation |
: |
Tehran
|
|
Delivery date |
: |
1999 |
|
Covered Area |
: |
36500 m² |
Scope
of work of APS for Gama Khodro Main Production Hall
Eng.
|
Supervision to
Execution
|
|
Concep. Des. |
Basic
Des. |
Detail Des.
|
M.C.
|
High Supervision
|
Site Supervision..
|
|
ü |
ü |
ü |
|
ü |
ü |
 |
8

|
Project Particulars |
|
Name of Project |
: |
Full Automatic
Paint Line with PLC Control System |
|
Employer |
: |
Pars Khodro |
|
Contractor |
: |
Asad Sanaat |
|
Location of
implementation |
: |
Tehran |
|
Delivery date |
: |
1998 |
Scope of work of APS for Paint Line With PLC Controlling
System
Eng.
|
Supervision to
Execution
|
|
Concep. Des. |
Basic
Des. |
Detail Des.
|
M.C.
|
High Supervision
|
Site Supervision..
|
|
ü |
ü |
ü |
|
ü |
ü |
 |
9
|
Project Particulars: |
|
Name of Project |
: |
Press Shop (Two
Lines of Presses for Forming the Hull of
Automobile) |
|
Employer |
: |
Pars Khodro |
|
Contractor |
: |
Maskan va
Navahi Sanati |
|
Location of
implementation |
: |
Tehran
|
|
Delivery date |
: |
2000 |
Scope of work of APS for Press Shop
Eng.
|
Supervision to
Execution
|
|
Concep. Des. |
Basic
Des. |
Detail Des.
|
M.C.
|
High Supervision
|
Site Supervision..
|
|
ü |
ü |
ü |
|
ü |
ü |
 |
110

BUSHEHR SHAHID MAHALLATI SHIPYARD
|
|
|
Project Particulars |
|
Name of Project |
: |
Mahallati
Shipyard |
|
Employer |
: |
Sepah Navy (NEDSA) |
|
Contractor |
: |
Omran Sahel |
|
Location of
implementation |
: |
Bushehr |
|
Delivery date |
: |
1998 |
|
Cost |
: |
50 Million USD |
Scope of work of APS for Mahalati Shipyard
Eng.
|
Supervision to
Execution
|
|
Concep. Des. |
Basic
Des. |
Detail Des.
|
M.C.
|
High Supervision
|
Site Supervision..
|
|
ü |
ü |
ü |
|
ü |
ü |
 |
11

|
Project Particulars |
|
Name of Project |
: |
I.O.O.C.
Extension Project |
|
Employer |
: |
Elf Petroleum
Iran |
|
Contractor |
: |
Tide Water |
|
Location of
implementation |
: |
Kharg Island |
|
Delivery date |
: |
2000 |
|
Cost |
: |
5 Million USD
(Estimated) |
Scope of work of APS for L.O.O.C. Extension Project
Eng.
|
Supervision to
Execution
|
|
Concep. Des. |
Basic
Des. |
Detail Des.
|
M.C.
|
High Supervision
|
Site Supervision..
|
|
ü |
ü |
ü |
|
ü |
 |
12
 
|
Project Particulars |
|
Name of Project |
: |
Dorood Project |
|
Employer |
: |
Elf Petroleum
Iran |
|
Contractor |
: |
Alisaz
Construction Company |
|
Location of
implementation |
: |
Kharg Island
|
|
Delivery date |
: |
2001 |
|
Cost |
: |
|
|
|
|
|
Scope
of work of APS for Dorood Project
Eng.
|
Supervision to
Execution
|
|
Concep. Des. |
Basic
Des. |
Detail Des.
|
M.C.
|
High Supervision
|
Site Supervision..
|
|
ü |
ü |
ü |
|
ü |
 |
13

|
Project Particulars |
|
Name of Project |
: |
Water Intake |
|
Employer |
: |
Total Fina Elf |
|
Contractor |
: |
Ali Saz |
|
Location of
implementation |
: |
Kharg Island |
|
Delivery date |
: |
2003 |
|
Cost |
: |
4 Million USD
|
Scope of work of APS for Water Intake
Eng.
|
Supervision to
Execution
|
|
Concep. Des. |
Basic
Des. |
Detail Des.
|
M.C.
|
High Supervision
|
Site Supervision..
|
|
|
ü |
ü |
|
ü |
ü |

|
14
|
Project Particulars |
|
Name of Project |
: |
Fiberglass
Passenger Craft |
|
Employer |
: |
Kerman Khodro |
|
Contractor |
: |
Kerman Khodro
Fiberglass industries Co. |
|
Location of
implementation |
: |
Kerman |
|
Delivery date |
: |
2000 |
|
Cost |
: |
|
|
Principal Particulars: |
|
Length Overal |
: |
23.0m |
|
LBP |
: |
21.0m |
|
Displacement Full |
: |
54.6 tonnes |
Scope of work of APS for Fiberglass Passenger Craft
Eng.
|
Supervision to
Execution
|
|
Concep. Des. |
Basic
Des. |
Detail Des.
|
M.C.
|
High Supervision
|
Site Supervision..
|
|
ü |
ü |
ü |
|
|
|
 |
15
ARVANDAN SHIPYARD AND REPAIR COMPLEX IN
ABADAN

|
Project Particulars |
|
Name of Project |
: |
Arvandan
Shipbuilding and Repair Complex in Abadan |
|
Employer |
: |
Arvandan Ship
Building Company |
|
Contractor |
: |
|
|
Location of
implementation |
: |
Abadan |
|
Delivery date |
: |
|
|
Cost |
: |
About 50
million USD (Estimated) |
Scope of work of APS for Engineering Services rendered
for the Project
Eng.
|
Supervision to
Execution
|
|
Concep. Des. |
Basic
Des. |
Detail Des.
|
M.C.
|
High Supervision
|
Site Supervision..
|
|
ü |
|
|
|
|
|

|
|
16
Drilling Operation Support Base

|
Project
Particulars
|
|
Name of Project |
: |
Drilling Operation Support
Base
|
|
Employer |
: |
KEPCO. |
|
Contractor |
: |
PANAH SAZ |
|
Location of
implementation |
: |
Neka |
|
Delivery date |
: |
2009 |
|
Cost |
: |
12 million USD
(Estimated) |
Scope of work of APS for Supervision
to EPC Contract
Eng.
|
Supervision to
Execution
|
|
Concep.Des. |
Basic
Des. |
Detail Des.
|
M.C.
|
High Supervision
|
Site Supervision..
|
|
ü |
ü |
ü |
ü |
ü |
ü |
 |
|
17
MAHBOOB LIAN NEW BUILDING AND REPAIR YARD

|
Project
Particulars
|
|
Name of Project |
: |
MAHBOOB LIAN NEW BUILDING AND REPAIR YARD |
|
Employer |
: |
MAHBOOB
LIAN Ship Building Company |
|
Contractor |
: |
Takvin Sanaat |
|
Location of
implementation |
: |
Bushehr |
|
Delivery date |
: |
1394 |
|
Cost |
: |
1,400,000,000,000 Rial |
Scope of work of APS for Engineering Services
rendered for the Project
Eng.
|
Supervision to
Execution
|
|
Concep.Des. |
Basic
Des. |
Detail Des.
|
M.C.
|
High Supervision
|
Site Supervision..
|
|
ü |
ü |
ü |
ü |
ü |
ü |
 |
|
18
Master Plan Of Persian Gulf Network

|
Project
Particulars
|
|
Name of Project |
: |
Master Plan of Persian Gulf Network Including Of Kaveh Port, Road, Railway and
Bridge Between Qeshm Island and Main land |
|
Employer |
: |
Qeshm
Free Zone Organization |
|
Contractor |
: |
Perto Sahel Tosee Khalij Fars |
|
Location of
implementation |
: |
Qeshm Island - Bandar Abbas |
|
Delivery date |
: |
1393 |
|
Cost |
: |
694,000,000
Euro |
Scope of work of APS for Supervision to EPCF Contract
Eng.
|
Supervision to
Execution
|
|
Concep.Des. |
Basic
Des. |
Detail Des.
|
M.C.
|
High Supervision
|
Site Supervision..
|
|
ü |
ü |
ü |
ü |
ü |
ü |
 |